One of the frequently asked questions is if there is a way to change the schedule used for a particular sequence when it's already running

Reply Team avatar
Written by Reply Team
Updated over a week ago

Yes, you can change schedules for active sequences. To change the schedule for any sequence:

  1. Open the list of your sequences by clicking on the Sequences page.

  2. Select the sequence in which you want to change the schedule by clicking on it.

  3. Open the Steps tab of the sequence interface.

  4. Click on the Sending schedule button in the upper right corner to select a new schedule from the drop-down list/customize the existing one:

Note: you must first create an alternate schedule to be able to select a new sequence schedule. To do this, navigate to the Schedules page of the Settings tab and click Create new schedule.